Platform installation · Support at height
Facade Access Platform and Gondola Installation
When a facade access platform is installed, the equipment is brought by the company that makes or rents the machine. The brackets at the roof edge, the anchor points drilled into the facade and the wind ties for the cradle, however, have to be fitted before the machine can run, and that is when our rope access team goes on site.
We work to the same plan as the installation crew of the manufacturer or contractor, and take on the jobs that have to be done on the facade and beyond the parapet.

Our Share in Installing an External Facade Platform
| Task | Manufacturer or rental company | Rope access team |
|---|---|---|
| Design and calculation | Defines the track route, the loads and the type of machine | Reports the facade and roof conditions at the site survey |
| Track and brackets | Supplies the parts and manages the installation on the roof | Fits the brackets and anchors that extend beyond the parapet |
| Cradle and suspension | Assembles the cradle and connects the suspension ropes and the controls | Accompanies the laying of the suspension line along the facade |
| Wind ties | Calculates the type and spacing of the ties | Installs the anchor sockets or guide rails on the facade |
| Testing and handover | Carries out the load test and commissions the machine | Descends to the inspection points and reports any defects with photos |
In the programme, platform installation usually starts before the facade cladding and the roof waterproofing are finished; the track brackets and anchors fall in the same weeks as those works. For that reason we work to a single programme with the facade contractor, the roof crew and the manufacturer. How the anchor holes join the waterproofing is resolved together at that point, so that they do not have to be opened up again later.
Facade Platforms: Roof Trolley on Rails, Monorail and Suspended Cradle
- 01
Roof trolley on rails
A machine with a jib that travels on rails on the roof. The parapet and edge details of the rails, and the anchors at the level the jib reaches, are fitted by rope.
- 02
Monorail system
A suspension trolley that moves along a single rail hung under the eaves or along the facade edge. The brackets that carry the rail are installed from outside the facade.
- 03
Davit arm and suspended cradle
A cradle hanging from fixed or portable arms on the roof. We descend the facade to anchor the arm bases and to fit the cradle’s wind ties.
Which of these systems, also known as a BMU, will be used is decided in the architectural design and the manufacturer’s calculation. We do not make that decision; we take on the part of the work done at height. When a system in an older building is being renewed, we also dismantle the existing rails and anchors with the same crew.
Installation Steps: From Site Survey to Load Test
- 1
Site survey and joint plan
The roof, parapet and facade are inspected on site; the order of work and the handover points of the two teams are written down.
- 2
Marking the points
The fixing positions on the manufacturer’s drawing are transferred to the facade and parapet, and the load-bearing elements are verified.
- 3
Drilling and anchoring
Chemical or mechanical anchors are fitted from outside the facade by technicians working on ropes.
- 4
Track and brackets
The parts on top of the roof are installed with the manufacturer’s crew; the parts that project over the facade are installed by rope.
- 5
Sealing
Every hole drilled into the facade and the base of every bracket is sealed against water.
- 6
Testing and handover
During the load test we descend to the inspection points on the facade and report any defects.
Reaching the Facade Before the Machine Runs
A facade platform cannot be used to install itself: the machine is not commissioned until the wind ties and the edge brackets are fitted. Reaching these points with scaffolding means erecting it over the whole height of the facade, and cherry pickers do not reach the upper floors of tall blocks.
Working from temporary anchors set up on the roof, the rope access team descends and finishes these jobs in the same programme as the platform. Once the machine is in service, we work with the same method on glass cleaning or silicone resealing in the corners and recesses the arm cannot reach.
On projects outside Ankara, the team stays on site for the whole installation programme.

Load Test, Documents and Handover File
From the manufacturer and the authorised body
- The machine’s conformity documents and operating manual
- The load test report from commissioning
- Periodic inspection records
From our team
- IRATA-certified technicians
- Personal equipment that meets EN 795, EN 361 and EN 1891
- The position, a photo and the installation record of every anchor fitted
Technical meeting
Let Us Add the Rope Access Team to Your Installation Programme
If you share the project drawings and the installation programme, we will work out together the jobs to be done at height and the number of people needed.